District

Alamogordo Public Schools

Location

Alamogordo, NM

Size

72,154 sqft

Project Type

Standards-based

Focus

Replacement building

Architect

Greer Stafford

SJCF Architecture

General Contractor

Jaynes Corp

Holloman Elementary School: Building a Strong Future

AWARD HISTORY

On September 19, 2018, the PSCOC allocated $2,120,881 for the planning and design of a replacement facility to the GSF pursuant to the Adequacy Planning Guide with a core capacity of 600 and initial classrooms for 500 students, grades K-5. At the time the award did not include demolition of the current school or changes to the field/track area.

Holloman ES Construction

PSCOC awarded the construction funding for this project in January of 2021, and a general contractor was selected in February (Jaynes Corp). In February, construction officially began with the laying of temporary fiber, phone lines, water, and sewage. 

In January 2023 the school received its Certificate of Occupancy, celebrating with a ribbon cutting ceremony. Construction was completed later in 2023.

Project Challenges During Design Phase

  • Located on Air Force base
  • Certain military requirements for on-base construction
  • Pumping of soils bridging
  • Limited site access
  • Defining district outside of adequacy items

Holloman Project Expenditures

Project Development/Professional Services $1,586,855.68
Quality Assurance/Pac, Tab, Roof Consultant $724,538.91
Construction $24,146,439.77
FF&E $585,410.89
Demolition $97,312.50
Actual’s to Date $24,146,439.77
Contigency $6,089,557.34
Project Budget $34,879,627.06